MTSU Radio Spectrograph Logbook 2016
Location:  MTSU Campus, Ezell Hall Room 120
           35.8 N, 86.4 W, Elev 163 m

Brief History
Summer-Fall 2015
Set up single frequency square dipole array 
Testing coaxial cable
Testing coaxial cable hybrid rings
Install FSX-6S switching spectrograph - confirmed 3-4 MHz bandwidth on wire dipoles

January - February 2016
Testing continues for spectrograph system
16-Feb-2016 Internet Switch causing much RFI

March 2016
13-Mar-2016  Install TFD Square array
Replaced Internet switch with Router
Install new shielded coax LMR 240
Install wide band 90-deg hybrid
Tested new TFD antenna system with FSX-6S spectrograph
17-Mar-2016  Success - all systems GO - First Light!
19-Mar-2016  First confirmed Solar data
23-Mar-2016  Full calibration
24-Mar-2016  First confirmed Jupiter data

April 2016
6-Apr-2016   Hard Drive issue Data not saved through 23-Apr-2016
24-Apr-2016  Scheduled Observation Timing issue

May 2016
1-May-2016   Data not saved through 17-May-2016
18-May-2016  Data issue resolved

June 2016
4-Jun-2016   Observation Timing error 
12-Jun-2016  Observation Timing resolved

July 2016
5-July-2016  Firewall issue resolved - data streaming working